24. A fixed deadline cannot accommodate all agreed requirements. How do you support a responsible scope decision?
HardChange & outcomes
Show model answer
Make the unmet needs, obligations, dependencies, and consequences visible. Work with delivery and operations to identify coherent release options, including a reduced scope, approved manual control, phased rollout, or changed date.
Explain residual risk and who must accept it; do not quietly remove important acceptance criteria to declare success. Update traceability and communications so users know which workflow is actually supported.
What interviewers listen for
- Compare coherent release options
- Name residual risk
- Preserve acceptance criteria