41. Two teams say they implemented the approved requirement but used different versions. What would you check?

MediumNeeds & requirements

Case
Show model answer

I'd identify the approved baseline, decision dates, change records and how updates reached each team. The issue may involve unclear authority, stale copies or an uncommunicated change rather than careless implementation by one side of the project.

I'd reconcile impacts and authorize controlled correction while preserving history. Overwriting an older document can hide decision differences and whether delivered behavior meets the current agreed scope and acceptance conditions.

What interviewers listen for

  • Identify decision-time approved versions
  • Trace communication and impacts
  • Preserve history during controlled correction