51. Why distinguish process touch time from the time a customer waits for the completed service?

EasyCommercial judgment

Technical
Show model answer

Touch time measures active processing within defined boundaries; elapsed customer time can also include queues, handoffs, transport, or rework. Reducing one activity’s effort may have little effect on the complete experience.

Map the actual flow and identify where delay occurs using suitable evidence. Avoid claiming an end-to-end improvement from a local efficiency figure unless the overall outcome was assessed under comparable conditions.

What interviewers listen for

  • Separate active work from total elapsed time
  • Identify queues, handoffs, and rework
  • Verify end-to-end effects of local improvements