13. A project is likely to miss its date. What would your update contain?
MediumDelivery & priorities
Managerial
Show model answer
Explain the current evidence, completed and remaining outcomes, the cause of uncertainty, and the consequences for dependent teams or customers. Show options such as scope adjustment, sequencing, added help where effective, or a changed date.
Recommend an option and state the decision needed. Avoid silently compressing tests or treating overtime as free capacity; keep the confidence and next checkpoint visible.
What interviewers listen for
- Evidence and consequences
- Feasible options
- Preserve quality and sustainability