50. Implementation is complete, but a required external approval has not arrived. How would you manage readiness?

MediumDelivery & reliability

Case
Show model answer

Keep implementation completion separate from authorization to release. Confirm the actual approval requirements, evidence submitted, accountable reviewer and unresolved questions without assuming that silence means approval.

Work on legitimate remaining readiness tasks and communicate the dependency and its effect on commitments. Escalate through the agreed process where appropriate, rather than bypassing the requirement or marking the release complete to match an internal milestone.

What interviewers listen for

  • Separate built from authorized to release
  • Confirm approval evidence and ownership
  • Report the unresolved dependency accurately