36. Why can a structure that is adequate in its completed state still need a separate construction-stage assessment?
MediumCivil infrastructure & built environment
Technical
Show model answer
Partially completed works may have different supports, connections, temporary loads and stability conditions. The final load-resisting system may not yet exist when materials or equipment are introduced.
Have qualified temporary-works and design owners assess the planned sequence and interfaces under applicable procedures. Do not infer construction safety from a final-state drawing or modify the sequence without reviewing its consequences.
What interviewers listen for
- Recognize different temporary load paths
- Review sequence and temporary works
- Do not infer safety from the completed state