34. Ground conditions encountered during construction differ from the design assumptions. What should happen next?
MediumCivil infrastructure & built environment
Case
Show model answer
Record the observed difference and identify work that depends on the affected assumption. Notify the responsible site and geotechnical design owners, using the project’s approved hold and change arrangements where required.
Obtain qualified reassessment and an authorized disposition before relying on the original design. Do not improvise a foundation adjustment or treat a nearby project’s soil report as proof that the discrepancy is harmless.
What interviewers listen for
- Preserve observed ground evidence
- Identify dependent work and responsible owners
- Require qualified reassessment and controlled change