85. A supplier reports 90% design completion because nine of ten drawings are done. What would you ask?
MediumEngineering delivery & collaboration
Case
Show model answer
Check the remaining drawing’s complexity, dependencies, maturity and review status, and whether completed drawings are actually approved. Equal document counts may bear little relationship to remaining technical effort or risk.
Use meaningful deliverables and acceptance evidence to update the forecast. Do not turn activity counts into a delivery assurance, especially when the last item controls procurement, integration or a required qualification decision.
What interviewers listen for
- Check technical maturity rather than document counts
- Assess remaining dependencies and risk
- Forecast from accepted deliverables and real effort