90. An engineering project has spent heavily but no longer meets the original service need. How would you recommend a reset?

HardEngineering delivery & collaboration

Managerial
Show model answer

Restate the current need and compare the remaining options using present evidence, future cost, technical risk and service value. Separate sunk expenditure from costs and consequences that can still change.

Present a feasible continuation, modification or stop recommendation with ownership and transition needs explicit. Preserve useful verified work without allowing prior effort or political commitment to conceal an option that cannot deliver the required outcome.

What interviewers listen for

  • Reassess the current need and feasible options
  • Separate sunk expenditure from future choices
  • Make transition and decision ownership explicit