43. A shift has 420 minutes of net production time and demand for 210 units. What is takt time, and how is it different from cycle time?

EasyProcess & industrial operations

Technical
Show model answer

Takt time is the demand-paced interval: 420 divided by 210 gives two minutes per unit. Cycle time describes how long a process or station actually takes under a stated definition.

Compare them with consistent time and product boundaries, including the effects of downtime, changeovers and yield. A nominal station cycle below takt does not alone establish that the whole operation can reliably satisfy demand.

What interviewers listen for

  • Calculate two-minute takt
  • Separate demand pace and actual process time
  • Check losses and system-level delivery