80. A team proposes a temporary deviation from a specification to keep work moving. What would you verify?
HardQuality & improvement
Case
Show model answer
I'd identify the requirement, affected scope, risk, duration and who can authorize the deviation. A temporary label does not remove consequences or make operational urgency sufficient evidence that the proposed exception is suitable for the product, customer or service involved.
I'd require qualified traceable approval, boundaries and expiry where appropriate. Preserve history and follow-up; one exception does not silently rewrite the specification or authorize every future case using the deviation.
What interviewers listen for
- Identify scope and authorization
- Use qualified traceable approval
- Preserve limits and original requirements