90. Ten orders were due; eight arrived on time and complete. What is the stated OTIF rate?
MediumDelivery & resilience
Technical
Show model answer
If each due order is one unit of measurement and eight meet both agreed conditions, on-time-in-full performance is 8 / 10 = 80%. I'd define the promise, completeness, tolerance, partial deliveries and denominator before comparing sites or periods.
I'd preserve promise history and inspect failures. Meeting time or completeness separately does not establish both together, and retrospective definition changes can mislead customers and teams about the actual service.
What interviewers listen for
- Calculate conditional 80%
- Require both conditions for each order
- Preserve definitions and promise history