35. Two teams each handle 30 cases per hour. When is adding their rates misleading?
MediumFlow & capacity
Case
Show model answer
Adding rates assumes work can be divided appropriately and both teams have the needed skills, inputs and support. Shared reviewers, uneven demand or different case types can prevent the combined system from completing 60 comparable cases per hour.
I'd model routing and shared constraints and compare completed quality work. Nominal staffing is not independent usable capacity, and a shared bottleneck can move rather than disappear when another team is added.
What interviewers listen for
- Check work comparability and routing
- Identify shared constraints
- Validate effective combined capacity