22. All workstreams report green, but the integrated milestone keeps slipping. How would you improve reporting?
MediumStakeholders & communication
Show model answer
Examine whether green means effort is underway or whether an accepted output is forecast on time. Review cross-team dependencies, integration work and inconsistent assumptions that may be invisible within individual reports.
Agree common status criteria tied to milestone evidence, remaining work and confidence. Report the integrated forecast with blockers and decisions, without penalizing early disclosure of risk. A useful status system should reveal problems soon enough to act.
What interviewers listen for
- Shared evidence-based status
- Integrated dependency view
- Reward early risk visibility