31. You inherit a project whose reports show progress that you cannot verify. How would you establish a trustworthy baseline?
HardBehavioral
Behavioral
Show model answer
Preserve existing records and compare claimed completion with deliverables, acceptance evidence, spending and team knowledge. Ask factual questions without presuming misconduct, and distinguish missing documentation from work that was never completed.
Create a reconciled baseline with confirmed, uncertain and incomplete items, plus a forecast based on remaining work. Escalate material discrepancies through appropriate governance and communicate corrections accurately. Do not backdate approvals or erase the earlier record to make the project appear consistent.
What interviewers listen for
- Preserve and reconcile evidence
- No unsupported accusation
- Transparent revised baseline
- Accurate historical record