4. What is the critical path?
MediumPlanning & scope
Show model answer
The longest sequence of dependent tasks, which determines the shortest possible project duration. Tasks on it have zero float, so any delay delays the project. Manage those tasks closely and consider fast-tracking or crashing them if the schedule is at risk.