91. An estimation model trained on previous projects predicts an aggressive date for a novel project. What would you examine?
HardAgile & methodologies
Technical
Show model answer
Compare the new scope, delivery environment, team capacity, dependencies, and work definitions with the training history. Check whether prior dates reflect reliable actuals or reporting incentives and whether the model’s uncertainty behaves sensibly on unfamiliar work.
Use independent estimates and sensitivity checks with qualified planners. Explain transfer limits and keep the model as evidence rather than treating historical predictive performance as a new commitment.
What interviewers listen for
- Check history quality and relevance to the new project
- Assess uncertainty on unfamiliar work
- Combine independent planning evidence without promising a date