88. An AI tool produces a detailed project plan with dependencies no team has confirmed. How would you use it?
MediumAgile & methodologies
Case
Show model answer
Treat the plan as a draft hypothesis and check activities, sequence, estimates, assumptions, owners, and approvals against authoritative project information. Plausible detail does not establish that a dependency exists or that a team has committed capacity.
Validate decision-critical elements with responsible people and record corrections. Use authorized inputs and keep the tool’s contribution visible rather than promoting generated dates or ownership assignments directly into the controlled baseline.
What interviewers listen for
- Treat generated dependencies as unverified hypotheses
- Validate dates, ownership, and assumptions
- Protect authorized data and baseline control