33. What makes an assumption log useful throughout a project rather than only at kickoff?

EasyPlanning & scope

Technical
Show model answer

Identify the assumption, its owner, supporting basis, consequences if wrong, and the point when it must be checked. Assumptions about access, demand, or another team’s delivery can expire as circumstances change.

Review decision-critical assumptions at relevant milestones and turn invalid ones into explicit changes, risks, or issues. A recorded assumption is not evidence that the dependency or approval it describes has actually been secured.

What interviewers listen for

  • Assign ownership and a validation point
  • Record consequences and supporting basis
  • Reassess assumptions when decisions or conditions change