77. A project improves one department’s performance but transfers substantial work to another. How would you report the outcome?

MediumStakeholders & communication

Case
Show model answer

Assess the end-to-end effect, including workload, service, cost, and who bears the change. Compare both departments against an appropriate baseline instead of counting local efficiency as an equal organization-wide benefit.

Work with benefit and operational owners to assess options and update the business case. Record material disbenefits and responsibilities, giving the decision maker a complete trade-off rather than hiding the transfer inside another team’s budget.

What interviewers listen for

  • Assess end-to-end value and transferred work
  • Use comparable baselines and responsible owners
  • Report benefits and disbenefits together