59. A project reports favorable earned-value indices, but completion percentages are based on optimistic opinions. How would you respond?
HardPlanning & scope
Case
Show model answer
Inspect how work earns value, whether the baseline represents the real scope, and what evidence supports reported completion. The indices can be mathematically correct while overstating actual accomplishment if their inputs are weak.
Agree appropriate objective measures and reconcile affected reports with work owners and project controls. Preserve the correction history and reassess the forecast rather than treating the existence of a formal metric as independent assurance of progress.
What interviewers listen for
- Audit how value is earned
- Reconcile progress with objective evidence
- Correct reports and forecast transparently