80. A senior stakeholder privately directs a workstream to change delivery priorities contrary to the approved plan. How would you handle it?
HardStakeholders & communication
Case
Show model answer
Clarify the requested change and its rationale, then assess the effect on commitments and dependent teams. Check the stakeholder’s actual authority rather than assuming seniority automatically overrides the agreed project governance.
Bring the concrete options to the appropriate decision route and document the result. Preserve necessary confidentiality without allowing private instructions to create a hidden parallel plan that other owners continue to forecast against incorrectly.
What interviewers listen for
- Clarify impact and actual decision authority
- Resolve through the agreed governance route
- Prevent hidden conflicting delivery plans