35. Two workstreams agree their own deliverables but neither owns the interface between them. How would you address it?

MediumPlanning & scope

Case
Show model answer

Define what must pass between the workstreams, its format, timing, quality conditions, and the joint outcome that demonstrates the interface works. Identify the missing integration work and the authority needed to assign it.

Agree accountable ownership and incorporate the work into both plans, estimates, and verification. A dependency line between completed components cannot substitute for the integration activity that makes the combined solution usable.

What interviewers listen for

  • Define the interface and joint success evidence
  • Assign integration ownership and capacity
  • Reflect the work in both plans and verification