41. Several projects claim the same improvement in a shared business metric. How would you make the program benefit case credible?

HardPlanning & scope

Technical
Show model answer

Define the outcome, baseline, population, timing, and causal assumptions with the benefit owner. Map each project’s contribution and shared dependencies, distinguishing enabling outputs from independently additive benefits.

Use a consistent program-level view and appropriate evaluation rather than summing every project’s full claim. Record attribution limits and who owns realization after delivery; a shared improvement cannot be multiplied simply because several teams contributed to it.

What interviewers listen for

  • Use a common baseline and benefit definition
  • Map shared dependencies and nonadditive contributions
  • Prevent double counting at program level
Several projects claim the same improvement in a shared business metric. How would you make the program benefit case credible — Project management interview que