68. What should happen to unresolved project risks when work transfers into operations?
MediumRisk & issues
Technical
Show model answer
Identify the remaining exposure, controls, warning signs, response resources, and accountable operational owner. Distinguish a completed project mitigation action from evidence that the underlying risk has disappeared.
Obtain the required informed acceptance or escalation under actual governance and retain the transfer record. Closing the project register should not silently remove a risk that the receiving team must still monitor and manage.
What interviewers listen for
- Describe remaining exposure and control limits
- Agree accountable operational ownership
- Record informed acceptance or escalation