65. Several project risks depend on the same subcontractor, but teams assess them separately. What would you review?

MediumRisk & issues

Case
Show model answer

Map the shared dependency, resource constraints, and failure pathways across workstreams. Separate risk entries may understate concentration or double-count mitigation benefits if every team assumes the same limited backup is available.

Coordinate an integrated assessment and credible response capacity with procurement and delivery owners. Keep conditional assumptions explicit rather than summing independent-looking scores or assuming distinct contracts imply independent delivery outcomes.

What interviewers listen for

  • Map common failure pathways and limited backups
  • Assess concentration across workstreams
  • Avoid false independence and duplicated mitigation capacity