82. How do throughput and cycle time describe different aspects of delivery flow?
EasyAgile & methodologies
Technical
Show model answer
Throughput counts completed items over a defined period; cycle time describes how long an item spends within defined start and finish boundaries. Their interpretation depends on stable definitions and the type and size of work counted.
Use them together with work in progress and quality evidence. A higher completion count does not establish faster delivery of comparable value if items were split differently or difficult work remained unfinished.
What interviewers listen for
- Define item, period, and timing boundaries
- Consider work size and work in progress
- Pair flow measures with value and quality evidence