84. Why might maximizing every specialist’s utilization make project delivery slower?

EasyAgile & methodologies

Technical
Show model answer

When heavily loaded resources receive variable or unexpected work, queues and waiting can grow. A plan that keeps everyone busy may leave dependent tasks blocked even while reported utilization appears excellent.

Examine bottlenecks, handoffs, work in progress, and suitable capacity buffers with the team. Optimize end-to-end delivery and sustainable commitments rather than treating idle-looking time as waste without considering its effect on responsiveness and flow.

What interviewers listen for

  • Distinguish local busyness from end-to-end flow
  • Investigate queues and bottlenecks
  • Use capacity deliberately rather than maximize utilization blindly