2. How do you handle scope creep?
MediumPlanning & scope
Show model answer
Keep a clear baseline scope and a change-control process. For each request, assess the impact on time, cost and quality, and let the sponsor decide: add it with more time or money, swap it for something else, or defer it. Document every decision.