24. The buyer wants to sign this month, but procurement has not started. How would you assess the close date?
MediumNegotiation & closing
Show model answer
Map the actual approval steps with the buyer: procurement intake, security or legal review, budget authorization and signature authority. Confirm owners and realistic durations instead of relying only on the requested date.
Build a mutual action plan backward from the target and identify what can run in parallel. Update the forecast if the evidence does not support the date. Provide complete approved materials promptly without implying that internal review controls can be bypassed.
What interviewers listen for
- Verified approval process
- Mutual dated actions
- Evidence-based forecast