67. A close plan ignores customer approval meetings, staff availability, and local working calendars. How would you reassess timing?
MediumSales process
Case
Show model answer
Confirm the actual decision steps and dates with the relevant customer owners rather than inferring availability from a country stereotype or the seller’s calendar. Identify dependencies that require work before an approval meeting can be meaningful.
Agree a realistic sequence and contingency points, then update the forecast. A target signature date is a planning preference until the necessary people, evidence, and authority can align within it.
What interviewers listen for
- Verify actual availability and decision steps
- Sequence prerequisite work before approvals
- Separate target dates from evidenced readiness