53. In a fictional steady-state process, stage 1 has two parallel workers handling 6 items/hour each; stage 2 handles 15/hour. Every item needs both stages. What is the capacity upper bound?
EasyCommercial judgment
Case
Show model answer
Stage 1 can process 12 items per hour and stage 2 can process 15, so the stated process is limited to 12 per hour. Adding capacity only to stage 2 would not raise that bound.
This assumes the stated rates, sufficient demand, compatible work, and no other constraints. Actual output can be lower because of variability, quality losses, or interruptions; the capacity calculation is not a guaranteed hourly production count.
What interviewers listen for
- Calculate stage capacities 12 and 15
- Identify 12/hour as the bottleneck bound
- Distinguish theoretical capacity from actual output