32. Three serial stages can process 60,40 and 50 units per hour. What is the simplified line capacity?

EasyFlow & capacity

Technical
Show model answer

If every unit passes through all three stages, with no losses or other constraints, capacity is limited to 40 units per hour. The fastest stage cannot make the whole line operate at 60 units per hour.

I'd check effective availability, work mix and changeovers before using that figure. The arithmetic is a simplified upper-bound model, not proof of actual sustained output, staffing sufficiency or delivered customer demand.

What interviewers listen for

  • Identify the 40-unit constraint
  • State serial-flow assumptions
  • Check effective operating conditions