33. With 480 available production minutes and demand for 120 units, what does takt time indicate?
EasyFlow & capacity
Technical
Show model answer
Takt time is available production time divided by demand, so 480 / 120 = 4 minutes per unit under these assumptions. It describes the pace needed to meet that demand, not the observed cycle time or a machine's rated capability.
I'd verify what available time excludes and how demand is defined. Comparing takt with process capability can guide questions, but does not authorize unsafe speeds or prove uniform product routing.
What interviewers listen for
- Calculate 4 minutes per unit
- Separate demand pace from capability
- Verify time and demand assumptions