13. What makes a dependency entry actionable rather than just a line in a schedule?
EasyPlanning & scope
Show model answer
Name the specific deliverable or decision required, the team providing it, the receiving task and the date it is needed. Agree what acceptable completion looks like and identify an accountable owner on each side.
Track evidence of progress and the impact of a slip, with an escalation point early enough to act. “Waiting on another team” is too vague to support coordination or a credible project forecast.
What interviewers listen for
- Specific deliverable and acceptance
- Provider and receiver owners
- Need-by date and escalation