12. How does a project risk differ from an issue, and what changes when a risk occurs?
EasyRisk & issues
Show model answer
A risk is an uncertain event or condition that could affect the project; an issue is a problem or condition already present. A possible supplier delay becomes an issue when the promised delivery is missed or the delay is confirmed.
Activate the planned response if suitable, assign an issue owner and reassess the impact on scope, schedule and cost. Continue tracking related risks rather than assuming the original entry alone manages the situation.
What interviewers listen for
- Uncertain versus present
- Activate and adapt the response
- Owner and impact update