25. You are asked for a fixed completion date before discovery is finished. How would you provide a useful forecast?

MediumAgile & methodologies

Show model answer

State what is known, the key assumptions and the uncertainties driving the estimate. Offer a range or scenarios with explicit scope and confidence rather than presenting a rough guess as a commitment.

Identify the short discovery work that could narrow the range and set a date for an updated forecast. If a fixed external date is unavoidable, explain the scope and risk choices needed to make it credible and name the decision owner.

What interviewers listen for

  • Assumptions and ranges
  • Work to reduce uncertainty
  • Separate forecast from commitment