25. You are asked for a fixed completion date before discovery is finished. How would you provide a useful forecast?
MediumAgile & methodologies
Show model answer
State what is known, the key assumptions and the uncertainties driving the estimate. Offer a range or scenarios with explicit scope and confidence rather than presenting a rough guess as a commitment.
Identify the short discovery work that could narrow the range and set a date for an updated forecast. If a fixed external date is unavoidable, explain the scope and risk choices needed to make it credible and name the decision owner.
What interviewers listen for
- Assumptions and ranges
- Work to reduce uncertainty
- Separate forecast from commitment