26. A go-live date is public, but rehearsal reveals data migration errors and an untested recovery plan. How would you lead the decision?
HardRisk & issues
Show model answer
Establish the affected data, operational consequences and evidence from the rehearsal with technical and business owners. Separate fixable defects from unknown recovery capability, and compare launch, reduced scope and delay against agreed acceptance criteria.
Bring a clear recommendation to the authorized go/no-go group with residual risks, owners and customer consequences. A public date does not remove acceptance gates. Require verified migration reconciliation and recovery evidence before claiming readiness, and prepare an accurate communication plan for the chosen path.
What interviewers listen for
- Evidence-based readiness
- Options and residual risk
- Authorized go/no-go
- Verified recovery