27. A critical supplier may stop trading before your project finishes. How would you respond while the information is uncertain?
HardRisk & issues
Show model answer
Verify the concern through appropriate commercial channels and assess current commitments, deliverables, access and dependencies. Involve procurement and relevant legal or finance owners without spreading unverified rumors or making unauthorized demands.
Develop options for continuity, such as securing usable completed work, qualifying alternatives and resequencing tasks. Compare transition time, cost and quality risks, then set triggers for switching plans. Track new evidence closely while preserving a workable relationship with the current supplier.
What interviewers listen for
- Verify and contain uncertainty
- Continuity options
- Switching cost and triggers
- Appropriate commercial ownership