28. Your program budget is reduced after several projects have started. How would you recommend what to stop, defer or protect?

HardPlanning & scope

Show model answer

Assess remaining cost, expected future value, obligations, dependencies and the consequences of stopping each project. Treat money already spent as historical rather than sufficient reason to continue, while including real shutdown and restart costs.

Build portfolio options that preserve coherent outcomes instead of cutting every project equally. Explain impacts on people, operations and benefits, and obtain decisions through program governance. Update baselines and communicate the rationale and review conditions to affected teams.

What interviewers listen for

  • Forward-looking value and cost
  • Portfolio dependencies
  • Coherent stop/defer options
  • Accountable rebaseline