16. Two critical tasks need the same specialist in the same week. How would you resolve the schedule?

MediumPlanning & scope

Show model answer

Verify the work, effort and actual availability with the specialist and task owners. Check dependencies and float; two tasks marked critical may reflect a schedule that has not yet accounted for resource constraints.

Compare resequencing, reducing scope, pairing another qualified person or changing the milestone. Show the effects on risk and delivery before seeking a priority decision. Do not solve the conflict by assigning the same person to two full-time commitments.

What interviewers listen for

  • Validate resource feasibility
  • Dependencies and float
  • Explicit schedule tradeoffs