16. Two critical tasks need the same specialist in the same week. How would you resolve the schedule?
MediumPlanning & scope
Show model answer
Verify the work, effort and actual availability with the specialist and task owners. Check dependencies and float; two tasks marked critical may reflect a schedule that has not yet accounted for resource constraints.
Compare resequencing, reducing scope, pairing another qualified person or changing the milestone. Show the effects on risk and delivery before seeking a priority decision. Do not solve the conflict by assigning the same person to two full-time commitments.
What interviewers listen for
- Validate resource feasibility
- Dependencies and float
- Explicit schedule tradeoffs