17. A project can deliver on time, but nobody owns whether the expected business benefit appears. What would you do?
MediumStakeholders & communication
Show model answer
Clarify the intended benefit, baseline, measurement window and operating changes needed after handover. Identify a business owner with authority over adoption and ongoing operations, rather than leaving the project team accountable for effects it cannot control.
Agree benefit review checkpoints and distinguish delivery acceptance from realized value. Include training, process changes and measurement in the transition plan. Report missing ownership as a governance gap before declaring the project successful.
What interviewers listen for
- Benefit baseline and timing
- Business owner
- Delivery versus realized value