18. A vendor says its work is complete, but your team cannot use the deliverable. How would you handle the disagreement?

MediumRisk & issues

Show model answer

Review the agreed scope, acceptance criteria and evidence with the vendor and receiving team. Separate an unmet commitment from an expectation that was never made explicit, and establish the operational impact.

Create a documented resolution plan with specific gaps, owners and dates, involving procurement or the contract owner as needed. Avoid informal acceptance simply to protect a milestone. Improve later handoffs with earlier demonstrations and clear acceptance checks.

What interviewers listen for

  • Compare with agreed acceptance
  • Distinguish gaps from new scope
  • Document resolution and authority