46. A resource plan counts every employee’s full working week as project capacity. What would you challenge?

MediumPlanning & scope

Case
Show model answer

Check business-as-usual work, leave, meetings, support duties, skill fit, and actual allocation authority. Nominal employment hours do not equal available productive project time, and one specialist cannot necessarily substitute for another.

Build a realistic capacity view with team managers and expose shortfalls early. Use transparent assumptions and sustainable commitments rather than solving the spreadsheet gap through invisible overtime or treating every scheduled hour as fully interchangeable.

What interviewers listen for

  • Separate nominal hours from usable capacity
  • Verify allocation authority and relevant skills
  • Expose shortfalls without hidden overtime
A resource plan counts every employee’s full working week as project capacity. What would you challenge — Project management interview question — Apexed