47. What checks would you make before trusting an updated project schedule?

MediumPlanning & scope

Technical
Show model answer

Check the status date, verified actual starts and finishes, remaining durations, logic, calendars, constraints, and resource assumptions. Ensure completed and future work are represented consistently rather than allowing dates to move without an explanatory basis.

Review changes to the driving paths and compare the forecast with source evidence from work owners. A saved scheduling file or refreshed chart is not proof that its inputs reflect actual progress.

What interviewers listen for

  • Validate actuals and remaining work at a defined cutoff
  • Review logic, resources, and driving paths
  • Reconcile the forecast with owner evidence