48. A schedule uses a long fixed lag between supplier delivery and deployment. How would you assess it?
MediumPlanning & scope
Case
Show model answer
Ask what actually happens during the gap: inspection, configuration, approval, transport, or waiting may require different owners and conditions. A single lag can hide work, resource needs, or uncertainty that should be visible.
Model substantive activities and dependencies explicitly where useful, retaining justified waiting periods separately. Confirm the supplier and receiving-team assumptions so a convenient calendar offset does not conceal the real source of the delivery constraint.
What interviewers listen for
- Identify work and waiting inside the lag
- Expose substantive owners and dependencies
- Validate supplier and receiving-team assumptions