37. A project has enough staff but repeatedly waits for unresolved design decisions. How would you improve the plan?
MediumPlanning & scope
Case
Show model answer
Map the decisions, required evidence, authorized owners, and latest useful dates against dependent work. Establish whether the blockage is missing information, competing criteria, unclear authority, or genuine unresolved trade-offs.
Schedule proportionate preparation and decision points with the responsible owners. Show the effect of delayed choices instead of adding more delivery tasks or pressuring teams to proceed on incompatible assumptions that will later require rework.
What interviewers listen for
- Plan decisions and evidence as real dependencies
- Identify the cause of indecision
- Show delay consequences and avoid incompatible assumptions