38. A project budget excludes the ongoing staff effort needed to operate the new service. What would you do?
MediumPlanning & scope
Case
Show model answer
Clarify the expected operating model, activities, capacity, skills, and cost owner with the receiving organization. Separate delivery expenditure from recurring effort without omitting either from the overall decision about viability.
Revisit the business case and transition plan with finance and operational owners. A project can finish within its delivery budget while leaving an unaffordable service, so make the ongoing obligation and required approval explicit.
What interviewers listen for
- Identify the recurring work and cost owner
- Distinguish delivery and ongoing economics
- Reassess viability and operational approval