54. A fictional project has planned value 100, earned value 80, and actual cost 100 in budget units. What do cost variance and CPI show?
EasyPlanning & scope
Case
Show model answer
Cost variance is earned value minus actual cost, or minus 20 budget units. The cost performance index is 80 divided by 100, or 0.8, indicating less budgeted work value achieved per unit of actual cost under the stated measurement.
Check credible completion evidence and the baseline. These figures do not directly state days late or establish future performance; they describe the stated cost-based measurement.
What interviewers listen for
- Calculate cost variance −20 and CPI 0.8
- Validate earned-value measurement and baseline
- Do not translate cost units directly into days