55. A fictional project has 40 units of actual cost, 30 for distinct committed remaining work, and 20 for other remaining work. What is its current estimated total cost?
MediumPlanning & scope
Case
Show model answer
If the three amounts are complete, comparable, and nonoverlapping, the estimate is 90 units. Confirm that the remaining-work figures include appropriate current assumptions rather than automatically adding the original budget again.
Reconcile commitments, accruals, risks, and scope changes with finance and delivery owners. Present the estimate’s basis and uncertainty; a correct addition does not establish that all future work or possible exposure has been captured.
What interviewers listen for
- Calculate 40+30+20=90 for distinct amounts
- Check overlap, completeness, and current assumptions
- Reconcile with finance and work owners